Commercial terms
Retention, advance payment, liquidated damages, VAT, withholding tax, minimum certificate and payment period: what each term does, with figures.
Every contract differs, so none of its money rules are fixed in HodariQ: they are typed on the contract's Commercial Terms tab (open the contract, press Details). Each payment certificate takes a copy of them and works out its figures from that copy. This page explains each term and the rule HodariQ applies; the certificate itself is explained under Valuations › How the certificate is worked out.
Retention
| Field | Rule |
|---|---|
| Retention % | Kept from the gross valuation to date of each certificate. |
| Retention limit (% of contract sum) | Retention stops growing once it reaches this share of the original contract sum (the Contract BoQ total). 0 means no limit. The amount is shown under it as Retention limit. |
| Retention on materials on site | Ticked: retention is also taken on materials on site. Untick when the contract takes retention on work done only. Shown with the Materials on Site feature. |
| Released at practical completion (%) | The share of the retention held that is paid back after practical completion. The rest is paid back when the defects liability period ends. |
| Materials on site: % allowed | The share of the value of materials delivered that is paid; proposed on every materials-on-site line of a valuation. |
Advance payment
Advance payment is one of No advance payment, % of contract sum (with Advance %) or Fixed amount (with Advance amount (fixed)). The resulting Advance amount is shown under it. With an advance, the contract shows an Advance Payment Certificate button once it is running; that certificate pays the advance on its own, and later certificates recover it.
- Advance recovered by: % of each gross valuation. Recovery to date is Recovery % of the gross valuation to date, never more than the advance paid.
- Advance recovered by: Equal amounts over a number of certificates. Recovery to date is the advance x the certificate number / Recovered over (certificates), never more than the advance paid.
- The Final Certificate always recovers whatever is left.
Good to know
HodariQ refuses terms that cannot work: a fixed advance of 0 (Enter the advance amount, or choose "No advance payment"), equal shares over fewer than one certificate, or a recovery % of 0 (the advance would never be recovered). Every percentage must be between 0 and 100, and periods and amounts cannot be negative.
Liquidated damages
Liquidated damages is the amount charged, Liquidated damages charged says per day or per week or part of a week, and Liquidated damages limit (% of contract sum) caps the total (the amount is shown as Liquidated damages limit). 0 means the contract has none. The damages run from the revised completion date (the completion date plus the days of granted extensions of time) to the valuation date, or to practical completion if that came first. Charged per week, part of a week counts as a whole week: 10 days late is 2 weeks.
A certificate can waive the damages of its own period; that is done on the certificate (Valuations topic).
Tax
- VAT: the firm's sales VAT added to the amount due of each certificate. Leave it empty for a VAT-exempt contract. Only percentage sales taxes of the firm are offered.
- Withholding tax %: kept by the employer when paying a certificate. 0 when it does not apply.
- Both are worked out on the amount due before VAT. With Damages after VAT and WHT ticked in Settings (the default), the damages of the certificate are taken off after the tax, so VAT and withholding tax are worked out on the amount due plus that certificate's damages.
Certificates
- Minimum certificate amount: an interim certificate whose amount due (before VAT) is below it cannot be certified; the message gives its amount and the minimum. 0 means no minimum. It does not apply to the advance payment certificate or the Final Certificate.
- Payment period (days): the days the employer has to pay a certified certificate. The due date is the certified date plus these days (see Money › Who owes what).
When terms change
A certificate copies the terms when it is made. While it is a draft, any change to the terms on the contract (and to the completion and practical completion dates) is copied again into the open draft at once. Once a certificate is submitted its copy is frozen, and a certified certificate never changes, so editing a contract later never rewrites a certificate already issued. Each change to a term is written in the contract's history with who made it.
Something unclear? Ask us on WhatsApp: we answer the same day.