Check a take-off
Catch a wrong scale, a drawing whose dimensions do not add up, and a careless click, before the quantities go out.
A take-off can be wrong three ways: the scale, the drawing, or the click. HodariQ gives a check for each.
1. The scale
- Read the pill: green is checked against the dimensions; orange means look again (see The scale).
- With Dimension click two or three dimensions in different parts of the page, one across and one down. Each should say as written; a warning means the scale, or that part of the drawing, is off by more than 1%.
- Read the message for Some dimensions are at another scale: a detail at another scale on the same sheet.
2. The drawing
Check Dimensions finds every chain of dimensions on a line whose ends meet, and the overall dimension spanning the same two ends on another line, and adds the chain up. Within 2 mm it shows a tick and as written; otherwise a warning: 2,360 + 3,600 + 2,400 = 8,360, but 8,400 is written. Click a check to have its overall dimension drawn on the plan.
Only the dimensions that agree on the scale most of the page's dimensions show are used, so a misread figure never gives a false alarm. A chain that does not add up is a question for the architect: raise it as a query on the spot.
3. The clicks
- Use Snap on CAD drawings: a snapped corner is exact, a free click is only as good as your hand and the zoom.
- At 100% one screen pixel is one drawing unit, about 35 mm on site at 1:100; at 400% about 9 mm. Zoom in for corners.
- Check the figure under each description: = 25.2 x 3 x 3 shows what was multiplied.
- Click p.1 on a row to see the measurement drawn on the plan; the selected one is drawn thicker.
Rounding
The points are kept to a hundredth of a drawing unit. Each quantity is rounded to 3 decimals (a millimetre for a length, a thousandth of a square or cubic metre for an area or a volume), and so is each row of the measurement sheet. The BoQ item's quantity is the total of its rows, rounded to 3 decimals: the figures on the screen, the dimension sheets and the BoQ are the same.
Before it goes out
- 1Print the marked drawing and look for anything measured twice or missed.
- 2Print the dimension sheets and check each Carried to the BoQ against the BoQ.
- 3Answer or close every open query, or list them as provisional in the BoQ.
Tip
Send the marked drawing with the dimension sheets to the checking QS: the checker sees where each quantity was measured without opening HodariQ.