Claimed and certified
When the other side's QS certifies: what was applied for and what was certified, side by side.
Both parties to a contract usually have a QS. One prepares the valuation, the other checks it, often reduces it, and certifies. HodariQ keeps both sets of figures on the same certificate, line by line, so the reductions are plain and can be argued.
Contractor firms
With Our applications are certified by the employer's QS ticked in Settings (contractor firms only, on by default), your valuation is an application until the employer's QS certifies it.
- 1Prepare the valuation as usual and press Submit.
- 2The approver presses Approve & Send to Employer. The valuation becomes Sent to employer, dated today. What you applied for is kept: each line's quantity or %, the materials on site and the amount due. The PDF now reads Interim Payment Application and we apply for payment of the sum, for certification by the Employer's Quantity Surveyor.
- 3When their certificate comes back, change the lines they reduced on Work Done and Materials on Site (only those), and type Employer's certificate / approval no. and Employer's certificate date. Application ref. keeps your own application number.
- 4A Senior QS / Manager presses Record Employer's Certificate. The certificate is certified, dated the employer's certificate date (or today), and the figures on screen are final.
The invoice is for what was certified, not for what was applied for, and the next valuation carries on from the certified figures. Back to Draft from Sent to employer clears what was kept, to prepare the application again.
Consultant firms
On a draft, type the amount due the contractor applied for in Applied for (amount due), under Applied for and certified on the Certificate tab of Details. The columns Claimed qty and Claimed % then open on the Work Done lines: type the contractor's figure on the lines where it differs from yours. The consultant certifies in one step, as usual. With the contractor portal, contractors send their claims online instead.
The figures kept
- Each claimed line: Applied for (claimed quantity × rate, or contract amount × claimed %), and Difference = certified less applied for, red when reduced.
- Applied for (gross): for an application sent by you, the claimed lines plus the materials applied for; for a claim typed by a consultant, the claimed lines plus the other lines and materials as certified (a line with no claimed figure is taken as certified as claimed).
- Difference (gross) = gross certified less applied for, and Lines reduced.
- Every change made after sending is kept in the line history.
Printing
Claim vs Certified in the Print menu lists only the lines where the two differ: Item, Description, Applied, Certified, the two amounts and the Difference, then gross applied for, gross certified, the difference, and the amounts due applied for and certified. When nothing was reduced it says every line was certified as applied for. A certified certificate with a claim also prints a short Applied for / Certified / Difference table under its figures.
Good to know
Variation orders work the same way: see Variations › Approving a variation order.
Something unclear? Ask us on WhatsApp: we answer the same day.