Cost plans
The elemental estimate before there is a BoQ: priced per m2, by quantity or as a lump sum, issued to the client, then checked against the BoQ.
Before there is a Bill of Quantities, the client asks what the building will cost. A cost plan prices it element by element (substructure, frame, roof...), adds preliminaries, contingency and VAT, and gives the cost per m2 of floor area. It stands on its own: no contract is needed. Once the project becomes a contract, the plan can be checked against the Contract BoQ.
Make a cost plan
- 1Go to Estimating › Cost Plans and press New.
- 2Type the Project, and choose the Client. Fill Location, Building type, Stage (Concept / feasibility, Scheme design or Detailed design), Date, Gross floor area (m2) and Storeys.
- 3On Elements, the usual 18 elements are already listed, each priced per m2 of floor area: Substructure, Frame, Upper floors, Roof, Stairs, External walls, Windows and external doors, Internal walls and partitions, Internal doors, Wall, Floor and Ceiling finishes, Fittings and furnishings, Sanitary appliances and plumbing, Electrical installations, Mechanical installations, Fire protection, External works and drainage.
- 4For each element choose how it is Priced and type the Rate; delete the elements the building does not have, add others, and add a Description of what is allowed for.
- 5Check Preliminaries (10%), Contingency (5%) and VAT (the firm's rate) under the elements, and write the Assumptions (prices at today's rates, exclusions such as land, fees and furniture).
- 6Press Print Cost Plan, then Issue to Client.
How it is worked out
| Priced | Amount |
|---|---|
| Per m2 of floor area | Gross floor area x rate. The quantity follows the floor area when it changes. |
| Quantity x rate | The element quantity typed, with its unit, x rate. It stays when the floor area changes. |
| Lump sum | The rate is the sum. |
- Building works = the sum of the elements. Each element shows its Per m2 GFA and its % of works.
- Preliminaries = % of the building works; contingency = % of building works plus preliminaries.
- Total (excl. VAT) = works + preliminaries + contingency; VAT = % of that total; Cost per m2 = total excl. VAT / gross floor area.
If the floor area grows to 1,200 m2, the substructure becomes 72,000,000 while the external works stay 20,000,000.
Issue, change, copy
- Issue to Client needs a priced plan (a total above 0). An issued plan is locked; to change it press Back to Draft, or copy it for a new estimate: the copy is a draft with a new reference and all the elements.
- Each plan has its own reference, CP-year-three digits.
- The print-out shows the project, client, location, building type, design stage, floor area and storeys, the elements with quantity, rate, amount and per m2, the estimated cost excluding and including VAT, the assumptions and exclusions, and Prepared by (Quantity Surveyor). A plan not yet issued is marked DRAFT.
Cost Check against the BoQ
On the Cost Check tab pick the Contract (this can be done even on an issued plan). Its Contract BoQ total appears beside the plan total with BoQ less plan (red when the BoQ is above the plan). Then, on a draft plan, match each element to the bills of the BoQ that price it: each element shows its BoQ amount and the difference, so you see where the BoQ is above the plan. The plan total includes preliminaries and contingency; the BoQ total includes its own.
Good to know
Cost plans come with the Cost Plans feature (Settings › Features, Professional plan). QS Officers and Senior QS / Managers make and issue them; Directors read them.
Something unclear? Ask us on WhatsApp: we answer the same day.