Pricing VO lines
Contract BoQ rates, library rates and star rates; omitting measured items and sums; % additions; the checks at Submit.
Every VO line is a quantity × a rate. Where the rate comes from decides what may be changed: an omission, or more of an existing item, keeps the contract rate; only new work gets a new rate. HodariQ checks these rules when the VO is submitted and again at every approval, so a VO that reaches the contract sum is always priced on the contract's terms.
How each line is priced
| Priced from | Used for | The rate |
|---|---|---|
| Contract BoQ rate | Every omission; more of an existing item | The item's contract rate, locked. Submit refuses a different rate on a measured item: use a star rate to agree a new one. |
| Rate library | An addition priced from your rate library (on the Additions tab of Details, on plans with the rate library) | Filled from the library rate, with its unit; can be changed. |
| Star rate (new, agreed) | Work the Contract BoQ does not have | Typed: the rate agreed with the other side. |
Every line's amount is quantity × rate. The VO's totals are: additions = sum of the added lines; omissions = sum of the omitted lines; net value = additions - omissions. Addition lines with no reference get one by themselves: VO-003/1, VO-003/2 and so on.
Measured items, sums and % additions
- A measured item is omitted by quantity at its contract rate. The quantity omitted can never exceed what is left of the item: the quantity let, plus approved additions of the same item at its contract rate, less what other submitted or approved VOs already omit.
- A Provisional Sum, PC Sum or Contingency is omitted by amount: its line has quantity 1 and you type the amount to take out in the Rate box (all of it, or the part used). It can never exceed what is left of the sum.
- When a VO with the reason Design change omits a provisional or PC sum, HodariQ asks once whether the sum is being spent; if it is, choose Provisional sum expenditure. A VO made from a revised drawing gets that reason by itself when it spends a sum.
- A % addition (profit, attendance on a PC sum) follows its item. If the VO changes an item that carries a % line, open Details and press Add the % Lines: the % lines come in as their own omissions or additions, worth the change of the item × the %. Submit refuses the VO until they are there.
- On plans with measurement sheets, the calculator button on a line in Details opens its dimension rows; their total becomes the line's quantity. Quick Measure on the Added sheet measures new work from a few dimensions.
What Submit checks
At Submit, and again at every approval, HodariQ refuses the VO when: it has no lines; a quantity is 0 or less or a rate is negative (something taken out is an omission line, never a negative quantity); a line is worth 0; an omission does not name its Contract BoQ item, or names an item of another BoQ; a Contract BoQ rate was changed; more is omitted than is left; or a % line is missing.