VO from revised quantities
Remeasured quantities compared item by item with the contract, turned into a draft VO at contract rates.
When the works are remeasured from revised drawings (in HodariQ, in Excel or in another measuring program), the new quantities do not have to be typed into a VO line by line. HodariQ compares each item with the quantity the contract has today and makes the omissions and additions for you, at contract rates.
Steps
- 1Open the contract's Details and press VO from Revised Quantities (running contracts, on plans with remeasurement).
- 2Under Revised quantities from choose Excel file (from Excel, CostX...) and pick the file (.xlsx or .xls, up to 15 MB), or Another BoQ of the contract and pick the remeasured BoQ (not the Contract BoQ itself).
- 3Check the VO title (Remeasurement from revised drawings by default) and type the Instruction, for example Architect's Instruction No. 7 with drawings Rev C.
- 4Choose what happens to Contract items not in the revised quantities: Leave them as they are when only part of the work was remeasured, or Omit them when the whole work was remeasured and they are no longer needed.
- 5Press Find the Changes. A summary says how many items were read, how many were found in the Contract BoQ, how many are unchanged and how many are new.
- 6Check the list. Untick Put in the VO on any line to leave it out; a star rate's description and rate can be changed. Back returns to the first step.
- 7Press Create Variation Order: a draft VO opens with the lines, ready to check, submit and approve as usual.
How the comparison works
Only measured items are remeasured: items, preliminaries and dayworks. Provisional sums, PC sums, contingencies and % additions are left alone; change them with their own VO lines if needed. In an Excel file, sheets named summary, collection, cover or contents are skipped, and each other sheet is read when it has column titles for Description and Quantity.
- Each revised row is matched to a Contract BoQ item by its reference (also written as bill/reference), or by its bill number and description. When a reference points to a different item than the description, the description wins: references are often renumbered in a revised BoQ.
- The quantity in the contract today = the quantity let + approved additions of that item - approved omissions of that item.
- Change = revised quantity - quantity in the contract today, to three decimals. More is an addition at the contract rate; less is an omission at the contract rate; no change, no line.
- A row the Contract BoQ does not have, with a quantity, becomes a new item priced at the rate in the file (a star rate, to be agreed), or with no rate when the file has none.
- A row matching an item already read is read once only; the duplicates are listed in the summary.
The screen shows for each line Qty in the contract, Revised qty, VO quantity, Rate and Amount, with Additions, Omissions and Net value at the top, and a Note where something needs a look:
| Note | What it means |
|---|---|
| The revised rate is ignored: the contract rate stands | The file has another rate for an existing item. Remeasurement never changes a contract rate. |
| Also changes this item and is not approved yet | Another VO, still open, changes the same item. Approve or drop one of them first, or the item may be changed twice. |
| Only part of the quantity let is left to omit | The omission is larger than what is left of the quantity let; the rest was added by an earlier VO and must be omitted by hand from that addition. |
| New item: agree this star rate / New item without a rate: price it | A new item, priced from the file or not priced at all. A line worth 0 is refused at Submit. |
A revised drawing in the take-off makes a VO the same way with Variation Order from Changes (see Take-off › Revised drawings).
Good to know
The draft VO is checked like any other at Submit: contract rates kept, nothing omitted twice, every line priced.