Extensions of time
The EOT register: requests, the days granted, and the revised completion date that liquidated damages run from.
An extension of time (EOT) moves the contract's completion date later. HodariQ keeps every request in a numbered register; only the days granted count. The completion date with the granted extensions, the revised completion date, is the date liquidated damages start from on the certificates.
Record a request
- 1Open Contracts › Extensions of Time and press New, or press Extensions on the contract's Details.
- 2Pick the Contract, the Date requested and the Reason: Variation order (extra work), Delay by the employer or the consultants, Exceptional weather, Unforeseen ground conditions, Force majeure or Other.
- 3For a variation order, pick the VO that caused the delay under Variation order. Type the Instruction / letter reference (for example the contractor's letter) and, under the form, what delayed the works and the evidence.
- 4Type the Days requested. Save: the request takes the next number of the contract, EOT-001, EOT-002 and so on, as Requested.
Grant or reject
Only a Senior QS / Manager decides. Days granted can be fewer than requested; left at 0, Grant gives all the days requested. Grant asks to confirm (the days move the completion date later), records the date decided and who decided. Reject sets the days granted to 0. Back to Requested reopens a decision made by mistake. While a request is open the form shows Completion date as before → after, so you see what granting it would do.
| State | Counts in the completion date | Can be changed |
|---|---|---|
| Requested | No | Yes, everything; can be deleted |
| Granted | Yes, the days granted | No: Back to Requested first (Senior QS / Manager) |
| Rejected | No | No: Back to Requested first; cannot be deleted |
The revised completion date
Revised completion date = the contract's completion date + the days granted on all granted extensions. Each granted EOT shows the completion date before it and after it, in register order. The contract shows Days granted (EOT), Completion (revised) and Days late: days past the revised completion date up to today, or up to practical completion once it is recorded.
With liquidated damages of 50,000 a day, a valuation dated 31/03/2026 was 21 days late before the extensions (1,050,000); with them it is 2 days late, 100,000. See Valuations and certificates › Liquidated damages.
What an extension changes
- Granting, or sending an EOT back to Requested, brings any draft valuation of the contract up to date at once: its completion date for damages, its days late and its damages.
- Certified certificates never change: they keep the completion date they were certified with. A later extension that cancels damages already deducted is given back through the next certificate, because damages are worked out to date (see Liquidated damages).
- Once the Final Certificate is submitted or certified, no extension can be granted, and decided ones cannot be reopened: the damages in the final account are settled.
Good to know
Granting an extension is a contract decision, usually by the architect or engineer on the QS's advice. Record it in HodariQ when it is decided, with the letter reference, so the certificates follow.