HodariQ
Ctrl K
Back to siteBook a demo

Getting started

  • How HodariQ works
  • Set up your firm
  • Country, currency and dates
  • Users and roles
  • Approvals
  • Sending documents: e-mail and WhatsApp
  • The change log
  • Plans and limits
  • Features and switches
  • What must come first

Contracts

  • Create a contract
  • Commercial terms
  • Key dates and contract states
  • The contract workspace
  • Programme of works
  • Parties
  • Completion and closing
  • Consultant or contractor firm

Bills of Quantities

  • Build a BoQ
  • Lines, sums and totals
  • Units
  • Measurement sheets
  • Import from Excel
  • How the import reads a file
  • Paste and copy
  • Rates and build-ups
  • Price list, regions and the Price Book
  • Print the BoQ
  • Export to Excel
  • Tender, lock and revise
  • Compare revisions

Take-off

  • Start a take-off
  • The screen, keyboard and tablet
  • The scale
  • Lengths, areas and counts
  • Rooms: one click or every room
  • Roofs and wall centre lines
  • Doors, windows and symbols
  • Assemblies
  • Heights from sections
  • Zones
  • Send to the BoQ
  • Print the take-off
  • Check a take-off
  • Revised drawings
  • Revision to a variation order
  • Queries to the architect
  • Quick Measure

Tenders

  • Tender analysis
  • Tenderers and their rates
  • Checks and ranking
  • Award and the tender report

Variations

  • Variation orders
  • Pricing VO lines
  • Approving a variation order
  • VO from revised quantities
  • The VO document and the register
  • Extensions of time

Valuations and certificates

  • The monthly valuation
  • How the certificate is worked out
  • Retention and its release
  • Advance payment and its recovery
  • Liquidated damages
  • Measurement sheets
  • Submitting, certifying and freezing
  • Claimed and certified
  • Printing certificates

Money

  • Invoices and payments
  • Withholding tax and VAT
  • Who owes what
  • Financial statement
  • Cost control
  • Budget line by line
  • Recording costs
  • LPOs (purchase orders)
  • Suppliers and their prices
  • Schedule of materials
  • Subcontracts
  • Subcontractor certificates
  • Cost plans

Site Portal

  • Add your site team
  • On site: the phone pages
  • The daily report from the phone
  • Chats and photos
  • Notifications on the phone
  • Material requests at the office
  • Who approves, and the settings
  • Daily reports at the office
  • Work done, item by item
  • Who sees what

Inbox and Work

  • How the Inbox works
  • Connect the mailbox
  • How e-mails are sorted, summarised and dated
  • Which contract an e-mail is about
  • Check and approve e-mails
  • My work: reply, notes and Done
  • Alerts, the morning e-mail and the contract

Bids and the NeST scout

  • How bids work
  • Bid or no bid, and the documents
  • Results, the win rate and the contract
  • The NeST scout
  • Bid alerts

Team

  • Team: who has how much work

Registers and alerts

  • Bonds, insurance and documents
  • Alerts
  • The dashboard and the financial statement
  • The contractor portal
Ctrl K
Docs/Contracts

Programme of works

The tasks in the order the job runs them, their dates in working days, the critical path, and how far the work is behind.

The programme says when each part of the job should be built. HodariQ keeps it next to the BoQ and the site reports, so it can tell how much of the work should be done by today and how much the site says is done.

Where it is

Open the contract and press Programme at the top of the contract workspace (or the Programme button on Details). Contractor and consultant firms both have it: a consultant QS can keep the contractor's programme to follow the job. QS Officers and Senior QS / Managers change it; Accounts and Directors see it.

Make it

  1. 1Press Make from the BoQ: one task per bill of the Contract BoQ, in the bill order, the first With the job and each other one After the bill before.
  2. 2Type each task's Length in working days. Leave it empty if you do not know it yet.
  3. 3Change Starts where the job runs differently: With the job (possession of site), After another task, with a lag of some working days, or On a date.
  4. 4Rename tasks, move them with the arrows, add a task with Add task (a task that is not a bill, such as a site hoarding, carries no value), remove a task with the bin. A task that waited on a removed one now follows what the removed one followed.
  5. 5Crew and Note for the planner are free text (2 gangs, before the rains).

How the dates are worked out

  • The job starts on Possession of site (else the contract date). Working days are the site's report days of Settings › Site Portal; when no report days are set, Monday to Saturday.
  • A task of 6 working days that starts on Monday 5 January 2026 ends on Saturday 10 January. The task after it starts on the next working day, Monday 12 January, plus its lag.
  • A task with no length has no dates, and every task after it shows Waits on that task.
  • A task cannot wait on itself, even through other tasks: HodariQ refuses it.
  • The last end date is the programme's end. When it is after the completion date (revised by extensions of time), Ends turns red and says by how many days.

Critical path and slack

The slack of a task is how many working days it can slip before a task after it, or the end of the job, moves. A task with no slack is on the critical path: its bar has a red outline. In the example, Substructure (6 days) and then the PC and Provisional Sums (3 days) end on 14 January and are both critical; a site hoarding of 2 days with the job ends on 6 January and has 7 working days of slack.

Should be done and done

Each task that is a bill is worth that bill of the Contract BoQ, less approved omissions. HodariQ spreads it evenly over the task's working days: by a date, a task should be done in the share of its working days gone. Should be done by today adds this up for all tasks, as a % of the Contract BoQ. Done (site reports) is the work the site reported item by item (see Work done, item by item) at contract rates, as a % of the same total. Certified to date is shown under it.

ExampleSubstructure, worth 15,022,500, on Wednesday 7 January
Should be done: 3 of its 6 working days (50%)7,511,250
Done: the site reported 60 of 120 m3 of excavation at 15,000 (6%)900,000
Behind by 44 pointsin Furthest behind

A task is in Furthest behind when the work done is a fifth of the task (20 points) or more behind what should be done by now; its row turns yellow and its Done red. The contract workspace shows the same two figures under Programme, in red when the job is 5 points or more behind.

The bar chart

One bar per dated task, with week marks, a black line for today and a red line for the completion date. The green part of a bar is the share done as reported by the site.

Good to know

Done counts only the site's reports; the programme does not move by itself when the work is late. Change the lengths or starts to re-plan: the dates, slack and critical path are worked out again at once.

← PreviousThe contract workspaceNext →Parties

Something unclear? Ask us on WhatsApp: we answer the same day.

On this page

  • Where it is
  • Make it
  • How the dates are worked out
  • Critical path and slack
  • Should be done and done
  • The bar chart