Revision to a variation order
On a running contract a revised drawing leaves the Contract BoQ alone and becomes a variation order at contract rates.
The Contract BoQ is locked: its quantities change only by variation order. So when a drawing measured into the Contract BoQ is revised, HodariQ compares the quantities of the two revisions item by item, and makes the variation order of the difference.
Steps
- 1Upload the revision with New Revision (see Revised drawings). The card says the Contract BoQ is locked.
- 2Work through every measurement marked To check: Measure again, Again with Room or Keep as is.
- 3The card lists each BoQ item that changed: BoQ item, Was, Now and Change, more in green, less in red. No BoQ quantity has changed yet means none.
- 4Press Variation Order from Changes. The draft variation order opens.
- 5Check it, add anything that is not measured, and submit it as any other variation order.
How the changes are worked out
- For each drawing HodariQ adds up the quantity of each BoQ item measured on it, deductions taken off.
- Change = the revision's quantity less the old drawing's, rounded to 3 decimals. Items that did not change are left out.
- More is an addition, less is an omission, of the difference, at the item's contract rate.
Block walling: Was412.300 m2
Now428.900 m2
Change+16.600 m2
Addition: 16.6 x TZS 32,500TZS 539,500
The variation order made
| Field | Filled with |
|---|---|
| Title | Revised drawing A-101 Ground floor plan Rev B |
| Reason | Design change |
| Instruction reference | A-101 Ground floor plan Rev B replacing A-101 Ground floor plan Rev A |
| Lines | One per changed item: addition or omission, its Contract BoQ item, description and unit, the change as quantity, the contract rate |
| History | The list of items with Was, Now and Change, made from the take-off |
Rules
- Variation Order from Changes waits until nothing is left To check: HodariQ names the measurements still to check.
- Measurements of this revision cannot be sent to the BoQ: Send is hidden. They go only into the variation order.
- One variation order per revision. Once it is made, the card shows a link to it and the revision becomes read only; if that VO is rejected, the revision opens again and a new one can be made.
- The contract must be running or practically complete. A locked BoQ on a contract not started is refused: start the contract first.
- Each revision is compared with the one before it: Rev C gives the changes since Rev B, not since Rev A.
Good to know
Only measurements that have a BoQ item count. A measurement with no BoQ item on either revision changes nothing in the variation order: choose its item before making it.
Something unclear? Ask us on WhatsApp: we answer the same day.