Budget line by line
Contractor firms: the client's BoQ against what each item costs you, the margin item by item, versions and approval.
The Contract BoQ says what the client pays. The budget says what the same work costs your firm. HodariQ keeps the two side by side, line by line, so you see the margin of every item and not only of the whole job: which items are below the margin you aim for, and which ones you will build at a loss. Some firms call it the office BoQ.
Where it is
Open the contract and press Budget at the top of the contract workspace (or Budget line by line on the Cost Control tab of Details). It needs a contractor firm, a locked Contract BoQ, a started contract and the Cost Control and Subcontracts feature. A Senior QS / Manager prepares and approves it; Accounts and Directors can open it once it exists, without changing it. QS Officers and the site never see it. All budgets of all contracts are listed under Money › Costs & Subcontracts › Budgets.
The first draft
- 1Press Budget. The first time, HodariQ makes Version 1 as a draft, one line per priced line of the Contract BoQ (less approved omissions) and one per approved addition of a variation order.
- 2Each line shows the client's Rate and Amount, then Our rate and Budget, then the Margin in shillings and %, and how the line was Costed by.
- 3Check the lines. Type your own rate in Our rate where you know better (a subcontractor's quote, a supplier's price); Enter goes to the next line. Clear the box to put back the rate HodariQ worked out.
- 4Change Target margin at the top right if this job aims for another margin than the firm's usual one.
- 5Press Approve the budget.
How each line is costed
| Costed by | When | Our rate |
|---|---|---|
| Build-up | The item has a library rate with a build-up (its own build-up for costing, or the rate it was priced from) | The build-up's materials, labour, plant, subcontract and overheads for one unit. Profit is not a cost. |
| At target margin | A measured item or preliminary without a build-up | The client's rate less the target margin |
| Paid at cost | A PC Sum or a Provisional Sum | The client's rate: the money is spent as it is paid, no margin is expected |
| Typed | You typed the rate | Your rate. It is kept when the budget is redrafted (shown with a tick). |
| Not a cost | Contingency, and % additions such as profit on a PC Sum | 0 |
The Target margin starts at the firm's Expected margin (Settings › Cost Control, 15%). Changing it on a draft budget costs again only the lines At target margin; build-ups, typed rates and sums at cost do not move.
Below target and at a loss
- At a loss: the line costs more than the client pays. Its margin shows in red, in brackets.
- Below target: the line makes money, but its margin % is under the target margin. A sum paid at cost and a line that is not a cost are never below target.
- The Watch figure at the top counts both; the buttons Below target and At a loss show only those lines. In the example, typing 16,000 on the excavation makes it a loss of 120,000; typing 14,000 makes it 6.7%, below the 15% target.
Approve, and what it changes
Approve the budget (Senior QS / Manager) freezes the version and makes it the contract's approved budget. The cost of every line is split by cost head (a build-up line in the proportions of its build-up; a line at target margin in Other costs, or Site overheads and preliminaries for a preliminary; a PC Sum in Subcontractors; a Provisional Sum in Other costs) and these totals replace the budget lines made from the BoQ on the Cost Control tab. Lines you added there yourself (site office, insurance) stay. From then on, Cost Control, the forecast final cost and the material requests count against the approved figures.
Versions
- An approved budget cannot be changed. When the job changes (an approved variation order, a better price), press New version: a draft Version 2 copies the approved lines with their typed rates, then adds the new variation lines and takes off approved omissions.
- Redraft on a draft brings it up to date with the Contract BoQ and the approved variations again; lines with a typed rate keep it, the others are costed again.
- Only one draft at a time. Approving it marks the version before Superseded; it stays readable in the version list at the top.
- Excel downloads the budget with formulas: quantity x rate on both sides, the margin and its %, and the totals.
Good to know
The budget is a planning figure: it posts nothing to the accounts. Quick budget from BoQ on the Cost Control tab still exists for a firm that only wants totals by cost head; approving a line budget replaces what it made.