HodariQ
Ctrl K
Back to siteBook a demo

Getting started

  • How HodariQ works
  • Set up your firm
  • Country, currency and dates
  • Users and roles
  • Approvals
  • Sending documents: e-mail and WhatsApp
  • The change log
  • Plans and limits
  • Features and switches
  • What must come first

Contracts

  • Create a contract
  • Commercial terms
  • Key dates and contract states
  • The contract workspace
  • Programme of works
  • Parties
  • Completion and closing
  • Consultant or contractor firm

Bills of Quantities

  • Build a BoQ
  • Lines, sums and totals
  • Units
  • Measurement sheets
  • Import from Excel
  • How the import reads a file
  • Paste and copy
  • Rates and build-ups
  • Price list, regions and the Price Book
  • Print the BoQ
  • Export to Excel
  • Tender, lock and revise
  • Compare revisions

Take-off

  • Start a take-off
  • The screen, keyboard and tablet
  • The scale
  • Lengths, areas and counts
  • Rooms: one click or every room
  • Roofs and wall centre lines
  • Doors, windows and symbols
  • Assemblies
  • Heights from sections
  • Zones
  • Send to the BoQ
  • Print the take-off
  • Check a take-off
  • Revised drawings
  • Revision to a variation order
  • Queries to the architect
  • Quick Measure

Tenders

  • Tender analysis
  • Tenderers and their rates
  • Checks and ranking
  • Award and the tender report

Variations

  • Variation orders
  • Pricing VO lines
  • Approving a variation order
  • VO from revised quantities
  • The VO document and the register
  • Extensions of time

Valuations and certificates

  • The monthly valuation
  • How the certificate is worked out
  • Retention and its release
  • Advance payment and its recovery
  • Liquidated damages
  • Measurement sheets
  • Submitting, certifying and freezing
  • Claimed and certified
  • Printing certificates

Money

  • Invoices and payments
  • Withholding tax and VAT
  • Who owes what
  • Financial statement
  • Cost control
  • Budget line by line
  • Recording costs
  • LPOs (purchase orders)
  • Suppliers and their prices
  • Schedule of materials
  • Subcontracts
  • Subcontractor certificates
  • Cost plans

Site Portal

  • Add your site team
  • On site: the phone pages
  • The daily report from the phone
  • Chats and photos
  • Notifications on the phone
  • Material requests at the office
  • Who approves, and the settings
  • Daily reports at the office
  • Work done, item by item
  • Who sees what

Inbox and Work

  • How the Inbox works
  • Connect the mailbox
  • How e-mails are sorted, summarised and dated
  • Which contract an e-mail is about
  • Check and approve e-mails
  • My work: reply, notes and Done
  • Alerts, the morning e-mail and the contract

Bids and the NeST scout

  • How bids work
  • Bid or no bid, and the documents
  • Results, the win rate and the contract
  • The NeST scout
  • Bid alerts

Team

  • Team: who has how much work

Registers and alerts

  • Bonds, insurance and documents
  • Alerts
  • The dashboard and the financial statement
  • The contractor portal
Ctrl K
Docs/Tenders

Checks and ranking

Corrected totals, arithmetic errors, unusual and unpriced rates, the threshold, and how tenderers are ranked.

Every figure of the analysis is worked out again on each change: a rate typed, a file read, a tenderer added or removed, the threshold changed. Nothing is ranked on the tenderers' own arithmetic.

The figures

FigureHow it is worked out
Correct amount of a lineBoQ quantity x the tenderer's rate, in whole shillings. For a % addition: the amount of its sum x the %.
Arithmetic errorThe tenderer wrote an amount on the line and it differs from the correct amount by more than 1 shilling.
Corrected totalThe correct amounts of every line added up, the QS's fixed sums included.
Arithmetic differenceCorrected total less the total as tendered (shown once the total as tendered is typed).
Average of a lineThe average of the rates (or %) of the tenderers that priced it. Unpriced rates are not counted.
From average (%)(Rate - average) / average x 100.
Check this rateThe rate is more than the threshold % above or below the average, or the line is not priced. Fixed sums are never marked.
RankTenderers that priced at least one line, lowest corrected total first.
Above lowestCorrected total less the lowest corrected total.

A worked example

The tender BoQ has Bill 2 (excavation 120 m3, hardcore 40.5 m3, concrete 30 m3) and Bill 11 (a PC Sum of 40,000,000 with a % for profit, attendance on it, a Provisional Sum of 20,000,000 and a Contingency of 10,000,000). Three tenders are read.

LineTenderer ATenderer BTenderer CAverage
2/A Excavation, per m315,00014,00024,00017,667
2/B Hardcore, per m345,00044,00046,00045,000
2/C Concrete, per m3380,000360,000390,000376,667
11/B Profit on the PC Sum5%4%5%4.67%
11/C Attendance500,000450,000not priced475,000
  • At 25%, Tenderer C's excavation at 24,000 is 36% above the average and is marked; Tenderer B's 14,000 is 21% below and is not. C's attendance is not priced and is marked. A and B have nothing to check.
  • At 10%, A's excavation (15% below), B's excavation (21% below) and B's 4% profit (14% below) are marked too. Changing the threshold marks the lines again at once.
  • The average of the attendance counts only the two tenderers that priced it: (500,000 + 450,000) / 2.
ExampleTenderer B, re-added
2/A 120 x 14,0001,680,000
2/B 40.5 x 44,0001,782,000
2/C 30 x 360,000 (B wrote 10,080,000: arithmetic error)10,800,000
11/A PC Sum, fixed40,000,000
11/B 4% of 40,000,0001,600,000
11/C Attendance450,000
11/D and 11/E Provisional Sum and Contingency, fixed30,000,000
Corrected total86,312,000
Total as tendered85,592,000
Arithmetic difference720,000
RankTendererCorrected totalAbove the lowestErrorsTo check
1Tenderer B86,312,000-10
2Tenderer A87,522,5001,210,50000
3Tenderer C88,443,0002,131,00002

Good to know

An unpriced line counts as nothing in a corrected total. A tender with lines left unpriced can therefore rank lower than it really is: read To check before reading the rank, and ask the tenderer whether the item is included elsewhere.

See every line

  • Comparison tab: one row per line with Ref., Description, Unit, Qty, the QS's rate, each tenderer's rate, then Lowest, Highest and Average; under them Total as tendered, Corrected total (quantity x rate), Arithmetic errors, Rates marked for checking, Above the lowest and Rank. Rates to check are shaded yellow and arithmetic errors red. Fixed sums have no lowest, highest or average.
  • Side by Side: a card per tenderer in rank order, with its corrected total, as tendered, how much above the lowest, its errors and rates to check; then every line grouped by bill with each tenderer's rate and its difference from the average. Errors are red, rates to check amber, fixed sums grey; point at a cell to read why. Tick Only lines to check to hide the rest. Details goes back to the form.

Tip

A rate far from the others is not wrong by itself: a low rate can be a mistake the tenderer will want to stand by after award. Note your findings in Notes: they print with the report.

← PreviousTenderers and their ratesNext →Award and the tender report

Something unclear? Ask us on WhatsApp: we answer the same day.

On this page

  • The figures
  • A worked example
  • See every line