Work done, item by item
The daily report says how much of each BoQ item was done; the certificate takes the figures in one click, and material requests are checked against the item's budget.
Besides the free text of the daily report, the site can say how much of each item of the Contract BoQ the team did that day. Added up, it is the work done to date as the site sees it: the programme compares it with what should be done, and the QS can put it into the next certificate instead of measuring again from nothing.
On the phone
- 1Open Daily report. Under Work done, item by item, type a few letters in Find the work and pick the item from the list. The items of the tasks on now in the programme are listed first.
- 2Type How much the team did today: a quantity in the item's unit (m3, m2, kg...), or a % of the item for a lump sum. The unit shows next to the box.
- 3Add other work for another item. A row left empty is ignored.
- 4Work done today can stay empty: the report then lists the items and quantities. Send the report as usual. Correcting the report the same day or the next replaces its rows.
The site never sees a rate or an amount: only the item's reference, description and unit.
Quantity or %
| Item | Reported as |
|---|---|
| A measured item (m3, m2, m, kg, No...) | The quantity done that day |
| A PC Sum, Provisional Sum, contingency, % addition or preliminary | The % of the item done that day |
| An item measured as one Sum or one Item | The % of the item done that day |
- To date is the sum of the days, never more than the whole item: 60 m3 then 100 m3 on an item of 120 m3 is 120 m3 to date, 100%.
- A day is more than 0 and at most 100% of an item. An item picked twice in one report adds the two.
- The rows count on the report's date, so a report of yesterday counts on yesterday.
Into the certificate
On a draft certificate, a Site column shows the work done to date reported up to the valuation date, in red where it differs from the figure typed. Differs from site shows only those lines. Use the site figures puts the site's figure into every line it reported: the quantity to date, or the % complete of a line valued by %. Lines measured on a measurement sheet keep their sheet, and lines the site did not report are not touched. Check every line before you submit: the site's figure is a report, the certificate is yours.
Material requests against the item's budget
In a material request, For which work offers the items of the Contract BoQ. When the site picks one, the office sees the request against that item's approved budget (see Budget line by line): Materials budget (the materials and plant of the item and of its approved variation additions), Asked before (the other requests for the same item, not rejected), and the % used With this one. It says Within budget or Over budget; the Approve window shows what is Left after this one. Only Senior QS / Managers, Accounts and Directors see these figures, and only once a budget is approved.
Something unclear? Ask us on WhatsApp: we answer the same day.