Liquidated damages
Days late from the revised completion date, per day or per week, the limit, practical completion, waivers and tax.
When the works finish after the revised completion date, the contract's liquidated damages are deducted on the certificates. HodariQ counts the days late on each valuation, applies the rate and the limit, stops at practical completion and keeps any waiver for good.
The terms on the contract
| Term | Default | What it does |
|---|---|---|
| Liquidated damages | 0 | The amount per day or per week. 0 means the contract has none and no line is printed. |
| Liquidated damages charged | per day | Or per week or part of a week. |
| Liquidated damages limit (% of contract sum) | 10 | Damages never exceed this share of the original contract sum. |
| Completion (contract) and Practical completion (actual) | The dates the damages run between, with the extensions of time granted. |
How they are worked out
- 1Revised completion date = the contract completion date + the days of the granted extensions of time (see Variations › Extensions of time).
- 2End = the valuation date, or the practical completion date if that came first.
- 3Days late = end - revised completion date, never below 0.
- 4Periods = the days late, or for a weekly rate the weeks with any part of a week counted as a whole week (8 days are 2 weeks).
- 5Damages earned to date = periods × the rate, never above the limit.
- 6Damages to date = earned to date less any damages waived. They are deducted in the net valuation to date; this certificate's damages are its to-date figure less the previous certificate's.
The certificate line reads, for example, Less liquidated damages (21 days late from 10/03/2026, 50,000 per day), with , at its limit when the limit is reached and , less followed by the amount waived when some were waived.
Waiving the damages of one certificate
When the employer waives the damages of a certificate, untick Deduct liquidated damages on the Certificate tab of Details (shown when the contract has damages). The damages for the days of this certificate are waived for good: what earlier certificates deducted stays deducted, and later certificates deduct only their own days.
VAT and withholding tax
Damages are damages, not a lower price. With Taken after VAT and WHT (damages are not a lower price) on in Settings › Certificates and printing (the default), VAT and WHT are worked out on the amount due plus this certificate's damages, then the damages come off. Untick it only if your tax adviser says the damages reduce the VAT; VAT and WHT are then on the amount due after the damages.
Edge cases
- Damages can make the amount due negative. With the same work on IPC No. 1 (dated 20/03, 500,000 of damages) and IPC No. 2 (dated 31/03, 1,050,000 to date), 1,800,000 less 10% retention on both, IPC No. 2 has an amount due of (550,000). With the damages after tax, the tax base is 0, so there is no VAT; the 550,000 is owed back.
- An extension granted later lowers the days late on the next certificate, and the damages already deducted come back through it, because damages are to date.
- On the Final Certificate the damages to date are shown again in the final account (Less liquidated damages) before the balance due.
- Once the Final Certificate is submitted or certified, extensions of time can no longer be granted or reopened.
Good to know
The contract shows Days late (to today, or to practical completion) and the damages deducted on the last certified certificate.