HodariQ
Ctrl K
Back to siteBook a demo

Getting started

  • How HodariQ works
  • Set up your firm
  • Country, currency and dates
  • Users and roles
  • Approvals
  • Sending documents: e-mail and WhatsApp
  • The change log
  • Plans and limits
  • Features and switches
  • What must come first

Contracts

  • Create a contract
  • Commercial terms
  • Key dates and contract states
  • The contract workspace
  • Programme of works
  • Parties
  • Completion and closing
  • Consultant or contractor firm

Bills of Quantities

  • Build a BoQ
  • Lines, sums and totals
  • Units
  • Measurement sheets
  • Import from Excel
  • How the import reads a file
  • Paste and copy
  • Rates and build-ups
  • Price list, regions and the Price Book
  • Print the BoQ
  • Export to Excel
  • Tender, lock and revise
  • Compare revisions

Take-off

  • Start a take-off
  • The screen, keyboard and tablet
  • The scale
  • Lengths, areas and counts
  • Rooms: one click or every room
  • Roofs and wall centre lines
  • Doors, windows and symbols
  • Assemblies
  • Heights from sections
  • Zones
  • Send to the BoQ
  • Print the take-off
  • Check a take-off
  • Revised drawings
  • Revision to a variation order
  • Queries to the architect
  • Quick Measure

Tenders

  • Tender analysis
  • Tenderers and their rates
  • Checks and ranking
  • Award and the tender report

Variations

  • Variation orders
  • Pricing VO lines
  • Approving a variation order
  • VO from revised quantities
  • The VO document and the register
  • Extensions of time

Valuations and certificates

  • The monthly valuation
  • How the certificate is worked out
  • Retention and its release
  • Advance payment and its recovery
  • Liquidated damages
  • Measurement sheets
  • Submitting, certifying and freezing
  • Claimed and certified
  • Printing certificates

Money

  • Invoices and payments
  • Withholding tax and VAT
  • Who owes what
  • Financial statement
  • Cost control
  • Budget line by line
  • Recording costs
  • LPOs (purchase orders)
  • Suppliers and their prices
  • Schedule of materials
  • Subcontracts
  • Subcontractor certificates
  • Cost plans

Site Portal

  • Add your site team
  • On site: the phone pages
  • The daily report from the phone
  • Chats and photos
  • Notifications on the phone
  • Material requests at the office
  • Who approves, and the settings
  • Daily reports at the office
  • Work done, item by item
  • Who sees what

Inbox and Work

  • How the Inbox works
  • Connect the mailbox
  • How e-mails are sorted, summarised and dated
  • Which contract an e-mail is about
  • Check and approve e-mails
  • My work: reply, notes and Done
  • Alerts, the morning e-mail and the contract

Bids and the NeST scout

  • How bids work
  • Bid or no bid, and the documents
  • Results, the win rate and the contract
  • The NeST scout
  • Bid alerts

Team

  • Team: who has how much work

Registers and alerts

  • Bonds, insurance and documents
  • Alerts
  • The dashboard and the financial statement
  • The contractor portal
Ctrl K
Docs/Valuations and certificates

Liquidated damages

Days late from the revised completion date, per day or per week, the limit, practical completion, waivers and tax.

When the works finish after the revised completion date, the contract's liquidated damages are deducted on the certificates. HodariQ counts the days late on each valuation, applies the rate and the limit, stops at practical completion and keeps any waiver for good.

The terms on the contract

TermDefaultWhat it does
Liquidated damages0The amount per day or per week. 0 means the contract has none and no line is printed.
Liquidated damages chargedper dayOr per week or part of a week.
Liquidated damages limit (% of contract sum)10Damages never exceed this share of the original contract sum.
Completion (contract) and Practical completion (actual)The dates the damages run between, with the extensions of time granted.

How they are worked out

  1. 1Revised completion date = the contract completion date + the days of the granted extensions of time (see Variations › Extensions of time).
  2. 2End = the valuation date, or the practical completion date if that came first.
  3. 3Days late = end - revised completion date, never below 0.
  4. 4Periods = the days late, or for a weekly rate the weeks with any part of a week counted as a whole week (8 days are 2 weeks).
  5. 5Damages earned to date = periods × the rate, never above the limit.
  6. 6Damages to date = earned to date less any damages waived. They are deducted in the net valuation to date; this certificate's damages are its to-date figure less the previous certificate's.

The certificate line reads, for example, Less liquidated damages (21 days late from 10/03/2026, 50,000 per day), with , at its limit when the limit is reached and , less followed by the amount waived when some were waived.

ExampleCompletion 10/03/2026, 50,000 per day
Valuation 31/03/2026, no extension: 21 days1,050,000
Same valuation, 19 days granted (revised completion 29/03/2026): 2 days100,000
Weekly rate of 300,000, valuation 18/03/2026: 8 days = 2 weeks600,000
Practical completion 15/03/2026, valuation 31/03/2026: damages stop after 5 days250,000

Waiving the damages of one certificate

When the employer waives the damages of a certificate, untick Deduct liquidated damages on the Certificate tab of Details (shown when the contract has damages). The damages for the days of this certificate are waived for good: what earlier certificates deducted stays deducted, and later certificates deduct only their own days.

ExampleA waiver on IPC No. 2
IPC No. 1 (20/03): 10 days, deducted to date500,000
IPC No. 2 (31/03): 21 days earned 1,050,000; its 11 days waived550,000 waived
IPC No. 2: deducted to date (nothing new)500,000
IPC No. 3 (10/04): 31 days earned 1,550,000, less 550,000 waived1,000,000
Deducted on IPC No. 3 alone500,000

VAT and withholding tax

Damages are damages, not a lower price. With Taken after VAT and WHT (damages are not a lower price) on in Settings › Certificates and printing (the default), VAT and WHT are worked out on the amount due plus this certificate's damages, then the damages come off. Untick it only if your tax adviser says the damages reduce the VAT; VAT and WHT are then on the amount due after the damages.

Edge cases

  • Damages can make the amount due negative. With the same work on IPC No. 1 (dated 20/03, 500,000 of damages) and IPC No. 2 (dated 31/03, 1,050,000 to date), 1,800,000 less 10% retention on both, IPC No. 2 has an amount due of (550,000). With the damages after tax, the tax base is 0, so there is no VAT; the 550,000 is owed back.
  • An extension granted later lowers the days late on the next certificate, and the damages already deducted come back through it, because damages are to date.
  • On the Final Certificate the damages to date are shown again in the final account (Less liquidated damages) before the balance due.
  • Once the Final Certificate is submitted or certified, extensions of time can no longer be granted or reopened.

Good to know

The contract shows Days late (to today, or to practical completion) and the damages deducted on the last certified certificate.

← PreviousAdvance payment and its recoveryNext →Measurement sheets

Something unclear? Ask us on WhatsApp: we answer the same day.

On this page

  • The terms on the contract
  • How they are worked out
  • Waiving the damages of one certificate
  • VAT and withholding tax
  • Edge cases