Roofs and wall centre lines
True lengths and areas up a roof slope, and walls measured round their face moved to their centre line.
A plan shows a roof flat and a wall by its faces. Two settings of a measurement, under Roof pitch, centre line of walls in its settings, turn what you measured on plan into what is built.
Roof pitch
Type the pitch in degrees in Pitch (degrees), from 0 to below 80. For an area the true area up the slope is the plan area divided by the cosine of the pitch. For a length, choose how it runs in Runs:
| Runs | True length | For |
|---|---|---|
| Level (ridge, eaves) | As on plan | Ridges, eaves, fascia, gutters |
| Up the slope | Plan length / cos(pitch) | Rafters, verges |
| Hip or valley | Plan length x the square root of (1 + tan2(pitch) / 2) | Hips and valleys |
The hip rule takes a hip running at 45 degrees on plan between two slopes of the same pitch, the usual hipped roof. For a roof whose slopes differ, measure each slope and work its hip by hand.
The table shows the true figure, with on plan beside it; the dimension sheets write both, e.g. 80.000 on plan x 1.1547 for a 30 degree pitch. An assembly on the roof uses the true area: the supplied Pitched roof covering assembly gives roofing sheets A and purlins A / 0.9.
Centre line of walls
The girth of a building is measured on its centre line for foundations and walling, but the plan is easiest to click on its outside or inside face. Measure the wall all the way round on one face, then set:
- Measured on: Outside face or Inside face (As measured leaves it alone).
- Wall thick (m): the wall's thickness.
HodariQ moves every side in (outside face) or out (inside face) by half the thickness, square to the side, and joins the corners again. For a rectangle this is the QS rule: the girth less, or plus, four times the thickness. It works for L-shapes and any other outline the same way.
Measured on the inside face instead, the 36 m becomes 36.800 m. The dimension sheets note: centre line of a 0.200 wall: 36.000 on its outside face.
Good to know
The centre line needs a closed outline: the last click must come back on the corner you started from (within 20 mm on site; Snap helps). Otherwise HodariQ refuses the setting and says so. With a height the centre-line length gives the walling, e.g. 35.2 x 3 = 105.6 m2.