Subcontractor certificates
The monthly valuation of a subcontractor's work, checked against what the employer has certified, then billed and paid.
A subcontractor payment certificate values the work done to date on a signed subcontract, less retention and the previous certificates, plus VAT, less withholding tax: the same steps as the employer's certificate, simpler (no advance and no materials on site). Beside each item it shows how much of the same BoQ item the employer has certified to you, so you do not pay for work you have not been paid for.
Value the work
- 1On the signed subcontract press New Payment Certificate. It is named Payment No. 1, 2... and copies the subcontract's retention %, VAT %, withholding tax % and payment period.
- 2Set the Valuation date.
- 3On Work Done, for each item choose the method (Quantity to date or % complete) and type the figure to date. Last month's figures are already there; Previous and This period follow.
- 4Look at Employer certified: an item valued further than the employer has certified for the same BoQ item is orange, and a note at the top says how many: Paying them means paying before we are paid.
- 5On the Certificate tab check the figures; set Retention released % when retention is paid back (for example 50 at practical completion, 100 at the end of defects liability). It stays in force on later certificates.
- 6Press Approve (Senior QS / Manager). It asks Approve this certificate? It is then final.
How it is worked out
Payment No. 2 with all 120 m3 done: work done 1,440,000, retention 72,000, net 1,368,000, less previous 684,000, amount due 684,000. With Retention released % at 50, retention to date falls to 36,000 and the amount due rises to 720,000.
Rules
- Certificates are made on a signed subcontract only, one draft at a time: an earlier certificate must be approved first.
- A certificate cannot be approved before its valuation date, nor dated before the previous certificate.
- An approved certificate is final: only its notes can be changed; corrections go into the next one.
- Back to Draft (Senior QS / Manager) is refused while it has a supplier bill that is not cancelled, or when a later certificate follows it.
- Only a draft certificate can be deleted.
- Approval counts the work as cost at once: cost to date takes the gross to date of the last approved certificate of each subcontract (retention included, as it is owed).
Bill and pay the subcontractor
- 1On the approved certificate press Create Supplier Bill (Accounts). The bill is dated today, due after the subcontract's payment period, with the reference contract, subcontract and certificate, the line Work done to date, less retention, less previous certificates, the subcontract's VAT and the contract's cost tracking account.
- 2Press Confirm on the bill.
- 3When paying, press Register Payment: it proposes the total less the withholding tax you keep, booked to Withholding tax payable (see Withholding tax and VAT).
A negative amount due becomes a supplier credit note; an amount due of 0 has nothing to bill. Pressing the button again opens the bill already made (Supplier Bill), and cancelling the bill lets the certificate be billed again. Print Certificate prints the Subcontractor Certificate, with signatures for the contractor and the subcontractor.
Good to know
Never enter a subcontractor's bill as a cost entry as well: it is counted through the certificate, and HodariQ refuses it.