The VO document and the register
The Variation Order PDF to sign, the variation register in PDF and Excel, and the running effect on the contract sum.
Every VO prints as a document to send to the other party and sign, and the contract keeps a register of all its VOs with the running effect on the contract sum.
The Variation Order PDF
Press Print on the VO screen (or Print Variation Order in Details). The document is laid out top to bottom:
- Your letterhead: firm name, address, phone and e-mail, registration and tax numbers, and the logo.
- The title Variation Order No. VO-001, with DRAFT under it while the VO is a draft.
- A heading table: Contract, Employer, Date instructed, Contractor, Instruction, Quantity Surveyor, Reason, Architect / Engineer, Status (with the employer's approval number when there is one) and Description (the VO title).
- Omissions: Ref., Description, Unit, Qty, Rate, Amount, with Total omissions.
- Additions: the same columns, each description followed by how it was priced (Contract BoQ rate, Rate library or Star rate), with Total additions.
- Total additions, Less total omissions and NET VALUE OF THIS VARIATION ORDER. When the VO was applied for and approved with other figures, Applied for and Difference (approved less applied for) follow.
- Effect on the contract sum: Original contract sum, Variation orders approved before this one, This variation order, and Revised contract sum including this variation order.
- Signatures: Prepared by and Approved for the Employer, each with Name, Signature, Date and Stamp.
The effect table counts only the VOs approved before this one in number order, so a reprint of VO-003 always shows the contract sum as it stood with VO-003, whatever came later.
The variation register
Contracts › Variation Orders lists every VO with its contract, number, title, Instruction, Date instructed, Additions, Omissions, Net value, Effect on contract sum to date and status. Filters show Draft, Submitted, Sent to employer, Approved or Rejected; group by Contract, Status or Reason. Effect on contract sum to date is the sum of the net values of the approved VOs up to and including that one; it is empty on a VO that is not approved.
On the contract, the Print menu has Variation Register: one row per VO with VO No., Title, Instruction, Date, Status, Additions, Omissions, Net, Effect to date and Reason (a rejected VO shows its rejection reason). Under the rows: Original contract sum, Approved variations, Revised contract sum and Variations waiting for approval. Variation register to Excel in the gear menu of the contract gives the same register as a spreadsheet.
| VO | Status | Net | Effect to date |
|---|---|---|---|
| VO-001 | Approved | 1,000,000 | 1,000,000 |
| VO-002 | Approved | 400,000 | 1,400,000 |
| VO-003 | Submitted | 250,000 |
Variations waiting for approval is the net value of the VOs in draft, submitted or sent to the employer: work you may still have to pay or be paid for, not yet in the contract sum.
Good to know
The register and the effect table count approved VOs only. A rejected VO stays in the register, greyed, so the file shows every instruction that was raised.