HodariQ
Ctrl K
Back to siteBook a demo

Getting started

  • How HodariQ works
  • Set up your firm
  • Country, currency and dates
  • Users and roles
  • Approvals
  • Sending documents: e-mail and WhatsApp
  • The change log
  • Plans and limits
  • Features and switches
  • What must come first

Contracts

  • Create a contract
  • Commercial terms
  • Key dates and contract states
  • The contract workspace
  • Programme of works
  • Parties
  • Completion and closing
  • Consultant or contractor firm

Bills of Quantities

  • Build a BoQ
  • Lines, sums and totals
  • Units
  • Measurement sheets
  • Import from Excel
  • How the import reads a file
  • Paste and copy
  • Rates and build-ups
  • Price list, regions and the Price Book
  • Print the BoQ
  • Export to Excel
  • Tender, lock and revise
  • Compare revisions

Take-off

  • Start a take-off
  • The screen, keyboard and tablet
  • The scale
  • Lengths, areas and counts
  • Rooms: one click or every room
  • Roofs and wall centre lines
  • Doors, windows and symbols
  • Assemblies
  • Heights from sections
  • Zones
  • Send to the BoQ
  • Print the take-off
  • Check a take-off
  • Revised drawings
  • Revision to a variation order
  • Queries to the architect
  • Quick Measure

Tenders

  • Tender analysis
  • Tenderers and their rates
  • Checks and ranking
  • Award and the tender report

Variations

  • Variation orders
  • Pricing VO lines
  • Approving a variation order
  • VO from revised quantities
  • The VO document and the register
  • Extensions of time

Valuations and certificates

  • The monthly valuation
  • How the certificate is worked out
  • Retention and its release
  • Advance payment and its recovery
  • Liquidated damages
  • Measurement sheets
  • Submitting, certifying and freezing
  • Claimed and certified
  • Printing certificates

Money

  • Invoices and payments
  • Withholding tax and VAT
  • Who owes what
  • Financial statement
  • Cost control
  • Budget line by line
  • Recording costs
  • LPOs (purchase orders)
  • Suppliers and their prices
  • Schedule of materials
  • Subcontracts
  • Subcontractor certificates
  • Cost plans

Site Portal

  • Add your site team
  • On site: the phone pages
  • The daily report from the phone
  • Chats and photos
  • Notifications on the phone
  • Material requests at the office
  • Who approves, and the settings
  • Daily reports at the office
  • Work done, item by item
  • Who sees what

Inbox and Work

  • How the Inbox works
  • Connect the mailbox
  • How e-mails are sorted, summarised and dated
  • Which contract an e-mail is about
  • Check and approve e-mails
  • My work: reply, notes and Done
  • Alerts, the morning e-mail and the contract

Bids and the NeST scout

  • How bids work
  • Bid or no bid, and the documents
  • Results, the win rate and the contract
  • The NeST scout
  • Bid alerts

Team

  • Team: who has how much work

Registers and alerts

  • Bonds, insurance and documents
  • Alerts
  • The dashboard and the financial statement
  • The contractor portal
Ctrl K
Docs/Valuations and certificates

Advance payment and its recovery

The advance payment certificate, and how each interim certificate recovers the advance.

When the contract gives the contractor an advance (mobilisation) payment, HodariQ issues it on its own certificate and then recovers it from the interim certificates, as the contract says, until all of it is back.

The terms on the contract

TermChoices and defaults
Advance paymentNo advance payment (default), % of contract sum or Fixed amount.
Advance %10 by default: advance = % × the original contract sum.
Advance amount (fixed)For a fixed amount; must be above 0.
Advance recovered by% of each gross valuation (default) or Equal amounts over a number of certificates.
Recovery %20 by default.
Recovered over (certificates)10 by default; at least 1.

Issue the advance payment certificate

  1. 1Open the contract's Details and press Advance Payment Certificate. The button shows on a running contract with an advance, until its certificate exists: a contract has one advance payment certificate.
  2. 2The certificate opens with no work lines. It reads Advance payment (10% of the contract sum), or (as agreed in the contract) for a fixed amount, then VAT and withholding tax as the contract has them, and the total payable.
  3. 3Submit and certify it like any certificate. Its PDF says the sum is due as advance payment.
ExampleAdvance Payment Certificate
Advance payment (10% of the contract sum of 850,000,000)85,000,000
Add VAT 18%15,300,000
Total amount payable100,300,000

How it is recovered

Advance paid on an interim certificate = the advance payment certificates certified when it is prepared (copied again while it is a draft and at Submit). Interim certificates certified before the advance recover nothing; the first one made after it catches up, because recovery is to date.

Recovered byAdvance recovery to date
% of each gross valuationRecovery % × gross valuation to date (materials on site included), rounded, never above the advance paid.
Equal amounts over a number of certificatesAdvance paid × the certificate's number ÷ the number of certificates, never above the advance paid. IPC No. 3 of 10 has recovered 3/10.
Final CertificateAll of the advance paid, whatever is left.

Recovery is to date, like retention: this certificate recovers its to-date figure less what the previous ones recovered, through the previous certificates line. The advance payment certificate itself is never part of previous certificates, so it is never taken off twice.

ExampleRecovery at 20% of gross on an advance of 85,000,000
IPC No. 1: gross 102,857,143, recovered to date20,571,429
IPC No. 2: gross 235,500,000, recovered to date47,100,000
Recovered on IPC No. 2 alone26,528,571
Still to recover after IPC No. 237,900,000
From a gross of 425,000,000: 20% reaches the advance and stays there85,000,000
ExampleEqual amounts over 4 certificates on an advance of 85,000,000
IPC No. 121,250,000
IPC No. 242,500,000
IPC No. 485,000,000
IPC No. 5 and later (never above the advance)85,000,000

On the certificate the line reads Less advance recovery 20% of gross, Less advance recovery (2 of 4) for equal amounts, or Less advance payment, recovered in full on the Final Certificate. The contract shows the advance still outstanding: advance paid less the recovery on the last certified certificate.

Good to know

An advance payment certificate cannot be made while another certificate of the contract is still open: finish that one first.

← PreviousRetention and its releaseNext →Liquidated damages

Something unclear? Ask us on WhatsApp: we answer the same day.

On this page

  • The terms on the contract
  • Issue the advance payment certificate
  • How it is recovered