Key dates and contract states
The Key Dates tab, the four states of a contract, what each one allows, and who moves it on.
A contract moves through four states: Draft, Running, Practically Complete and Closed. The state decides what can be made on it and who may change it. States change only through the buttons; a status typed into an import or changed in any other way is refused, because the buttons are where HodariQ checks who may and when.
The Key Dates tab
| Field | What it holds |
|---|---|
| Tender Date, Contract Date | The contract date cannot be before the tender date. |
| Possession of site | The start of the works. Until the first certificate, the valuation reminder counts from it. |
| Completion (contract) | Must be after possession of site. |
| Contract period (weeks) | Type the weeks and the completion date is worked out from possession of site; type both dates and the weeks are worked out (rounded). |
| Days granted (EOT) and Completion (revised) | Shown once an extension of time is granted: the completion date plus the days granted. Liquidated damages and the reminders use the revised date. |
| Practical completion (actual) | Filled when practical completion is recorded. Cannot be before possession of site. |
| Defects liability period (months) | 12 by default. |
| Defects liability ends | Practical completion plus the defects liability months, worked out by HodariQ. |
The four states
| State | What can be done | Who moves it on |
|---|---|---|
| Draft | Prepare everything: parties, dates, terms, BoQs (New BoQ on the workspace). No variation order or certificate yet. A QS Officer may edit it. | Start Contract: Senior QS / Manager |
| Running | Valuations (New Valuation, Next valuation), the advance payment certificate, variation orders, extensions of time, invoices, costs and subcontracts. Terms changed by a Senior QS / Manager only. | Practical Completion: Senior QS / Manager |
| Practically Complete | The same, plus Final Account. Retention release and the defects liability period run. | Close Contract: Senior QS / Manager |
| Closed | The contract is settled. Money still owed on its certificates is still followed up. | Reopen only |
Start the contract
A draft contract shows a Ready to start checklist on its workspace and its form: Contract BoQ locked, Contractor chosen and Contract date, possession and completion, each with a tick or a button (Open the BoQ, Fill in). Start Contract checks the same things and says what is missing, for example Fill in before starting the contract: Contractor, Possession of site. Without a locked Contract BoQ it says Lock a priced BoQ as the Contract BoQ first: the contract sum comes from it. The original contract sum is always the total of the Contract BoQ; the revised contract sum adds the approved variation orders.
Going back a step
Reopen (Senior QS / Manager) takes the contract back one state, for a status set by mistake:
- Running to Draft only while the contract has no variation order and no certificate; otherwise HodariQ refuses it.
- Practically Complete to Running clears the practical completion date, so liquidated damages run again.
- Closed to Practically Complete.
Archive or delete
Only a draft contract can be deleted, by a Senior QS / Manager. A started contract is archived instead: it leaves the lists but keeps all its documents; the Archived filter shows it again. The Contracts list filters by Draft, Running, Practically Complete, Closed and Archived, and groups by Status, Employer or Region; its columns show the contract sum, the certified % and the state.