Schedule of materials
The materials, labour and plant a BoQ needs, worked out from the rate build-ups, with what is bought and still to buy.
The schedule of materials, labour and plant turns a priced BoQ into what must be ordered and hired: 30 m3 of concrete priced from a build-up of 7 bags of cement a m3 needs 210 bags, plus the build-up's wastage. It needs the Rate Library feature, because the quantities come from the build-ups of the library rates.
Open it
- On any BoQ, press Schedule of Materials (QS Officer and above).
- On a running contract, press Schedule of Materials on the Cost Control tab: it opens the schedule of the Contract BoQ.
The window shows Measured work, With a build-up and Cost of these resources, then one line per resource: Type, Code, Resource, Unit, Net quantity, Wastage (optional), To order, Unit cost, Cost, and on a Contract BoQ with purchases Bought and Still to buy. Choose a Bill (empty: the whole BoQ) and what to Show (Everything, Material, Labour, Plant, Subcontract), then press Show. Print PDF and Excel give the same schedule, grouped by type.
How the quantities are worked out
- Net quantity = BoQ quantity x the quantity a unit of the build-up line, summed over every item that uses the resource.
- To order = net quantity plus the wastage % of each build-up line.
- Cost = BoQ quantity x the build-up line's amount; Unit cost = cost / to order.
- Which build-up: the one chosen on the line as Build-up for costing, else the library rate the line was priced from, when that rate has a build-up.
- Which quantities: the BoQ's. On a Contract BoQ, approved variation orders count: omissions take quantity off the item, additions bring their own build-up (their library rate, or the build-up of the BoQ item they extend).
- Only measured work (items, preliminaries, dayworks) is scheduled. PC and Provisional Sums and contingency are not the contractor's own resources and are left out.
- Resources are listed materials first, then labour, plant and subcontract, by code.
Items without a build-up
When measured items have no build-up, a yellow note says how many, and that the schedule covers only part of the measured work (the % shown). Its Link Items to Build-ups button (also Link to Build-ups on the BoQ) opens a window that matches each such item with the library rate that fits it best:
- The match compares the words of the description and the unit. Another unit never matches; different figures (grade 25 against grade 30, 150 mm against 200 mm) weigh against.
- Each row shows the Library rate, its Match % and Match: Good (60% and over), Check, or None found (no rate under 35% is proposed).
- Only a sure match (100%) is ticked for you. Tick Link on the others after a look, change a rate where needed, and press Link. Choosing a rate in another unit warns that the quantities would be wrong.
Linking changes no rate and no amount of the BoQ, so it is allowed on a locked Contract BoQ; it only tells the budget and the schedule which build-up to use. The BoQ's history notes how many items were linked.
Good to know
Unit costs and costs are shown only to users who see rate build-ups (Rate build-ups and margins, Senior QS / Manager, Accounts, Director). A QS Officer sees the quantities, and the print-outs leave the costs out for them.